HF4560
Technical and clarifying changes to statutes related to Public Utilities Commission made.
Legislative Session 94 (2025-2026)
Related bill: SF4590
Bill text
(underlined = new law, struck through = current law the bill removes)
Versions
1.1A bill for an act
1.2relating to energy; making technical and clarifying changes to statutes related to
1.3the Public Utilities Commission; amending Minnesota Statutes 2024, sections
1.4216.13; 216.16; 216.161; 216.17, subdivision 3; 216A.01; 216A.03, subdivisions
1.51, 6; 216A.05, subdivision 2; 216B.027, subdivision 7; 216B.06; 216B.098,
1.6subdivision 2; 216B.16, subdivision 19; 216B.1611, subdivision 3a; 216B.2412,
1.7by adding a subdivision; 216B.2422, subdivision 3; 216B.27, subdivisions 1, 2,
1.83, 4, 5; 216B.43; 216B.62, subdivision 3a; repealing Minnesota Statutes 2024,
1.9sections 216B.1681; 216B.1695; 216B.2412, subdivision 3.
1.10BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.11Section 1. Minnesota Statutes 2024, section 216.13, is amended to read:
1.12216.13 COMMENCING PROCEEDINGS BEFORE COMMISSION.
1.13Proceedings before the commission deleted text begin against any such carrier or public warehouse operator deleted text end
1.14shall be instituted by new text begin a new text end complaint deleted text begin , verified as a pleading in a civil action, stating deleted text end new text begin or petition new text end
1.15 new text begin that states new text end in ordinary language the facts constituting the alleged omission or offense new text begin or new text end
1.16 new text begin action requested. The filer must provide notice to the affected utilities new text end . deleted text begin The parties to such deleted text end
1.17 deleted text begin proceedings shall be termed, respectively, "complainant" and "respondent." deleted text end
1.18Sec. 2. Minnesota Statutes 2024, section 216.16, is amended to read:
1.19216.16 HEARINGS BEFORE COMMISSION.
1.20If the deleted text begin matter be deleted text end new text begin complaint or petition is new text end not adjusted to the satisfaction of the commission,
1.21 deleted text begin it deleted text end new text begin the commission new text end shall set a time and place of hearing, and give at least ten days' notice
1.22thereof to each party. The parties may appear either in person or by attorney. The commission
1.23shall hear evidence and otherwise investigate the matter, make findings of fact upon all
1.24matters involved, and such order or recommendation deleted text begin in the premises deleted text end as may be just. A copy
2.1of such findings and order or recommendation shall forthwith be served upon each party.
2.2No proceedings shall be dismissed on account of want of pecuniary interest in the complaint.
2.3Sec. 3. Minnesota Statutes 2024, section 216.161, is amended to read:
2.4216.161 CONTESTED CASES; NOTICE.
2.5Notwithstanding the provisions of any other law the commission in any contested case
2.6shall give reasonable notice to representatives of associations or other interested groups or
2.7persons who have registered their names with the new text begin executive new text end secretary of the commission
2.8for that purpose, to all parties and to cities and municipalities which the commission deems
2.9to be interested in the proceeding. The commission may prescribe an annual fee to be paid
2.10into the state treasury which shall be a charge to all registered groups or persons. This charge
2.11is to cover the costs involved.
2.12"Contested case" deleted text begin means a proceeding before the commission in which the legal rights, deleted text end
2.13 deleted text begin duties or privileges of specific parties are required by law or constitutional right to be deleted text end
2.14 deleted text begin determined after a hearing deleted text end new text begin has the meaning given in section 14.02, subdivision 3 new text end .
2.15Sec. 4. Minnesota Statutes 2024, section 216.17, subdivision 3, is amended to read:
2.16Subd. 3. Filings with commission; manner of filing. deleted text begin As of January 1, 2008, deleted text end Any
2.17telephone company or telecommunications carrier subject to chapter 237; any public utility,
2.18cooperative association, or municipal utility subject to chapter 216B; and state agencies,
2.19shall file documents with the commission via the commission's electronic filing system.
2.20The executive secretary may approve an exemption from this requirement if an affected
2.21company or agency is unable to submit filings via the commission's electronic filing system.
2.22All parties, participants, or other interested persons shall submit filings to the commission
2.23via the commission's electronic filing system whenever practicable, but may also file by
2.24personal delivery or by mail.
2.25Sec. 5. Minnesota Statutes 2024, section 216A.01, is amended to read:
2.26216A.01 DEPARTMENT AND COMMISSION; POWERS AND DUTIES.
2.27The Department of Commerce shall have and possess all of the rights and powers and
2.28perform all of the duties vested in it by this chapter. The Public Utilities Commission shall
2.29have and possess all of the rights and powers and perform all of the duties vested in it by
2.30 deleted text begin this chapter and those formerly vested by law in the Railroad and Warehouse Commission deleted text end
2.31 new text begin chapters 216, 216A, 216B, 216C, 216G, 216H, 216I, and 237 new text end .
3.1Sec. 6. Minnesota Statutes 2024, section 216A.03, subdivision 1, is amended to read:
3.2Subdivision 1. Members. The Public Utilities Commission shall consist of five members.
3.3The terms of members shall be six years and until their successors have been appointed and
3.4qualified. Each commissioner shall be appointed by the governor by and with the advice
3.5and consent of the senate. Not more than three commissioners shall belong to the same
3.6political party. At least one commissioner must have been domiciled at the time of
3.7appointment outside the seven-county metropolitan area. deleted text begin If the membership of the deleted text end
3.8 deleted text begin commission after July 31, 1986, does not consist of at least one member domiciled at the deleted text end
3.9 deleted text begin time of appointment outside the seven-county metropolitan area, the membership shall deleted text end
3.10 deleted text begin conform to this requirement following normal attrition of the present commissioners. deleted text end The
3.11governor when selecting commissioners shall give consideration to persons learned in the
3.12law or persons who have engaged in the profession of engineering, public accounting,
3.13property and utility valuation, finance, physical or natural sciences, production agriculture,
3.14or natural resources as well as being representative of the general public.
3.15For purposes of this subdivision, "seven-county metropolitan area" means Anoka, Carver,
3.16Dakota, Hennepin, Ramsey, Scott, and Washington Counties.
3.17Sec. 7. Minnesota Statutes 2024, section 216A.03, subdivision 6, is amended to read:
3.18Subd. 6. Record of proceedings. An audio deleted text begin magnetic or audio electronic deleted text end new text begin or video new text end
3.19recording device shall be used to keep a record of all proceedings before the commission.
3.20Sec. 8. Minnesota Statutes 2024, section 216A.05, subdivision 2, is amended to read:
3.21Subd. 2. Powers generally. The commission shall, to the extent prescribed by law:
3.22(1) investigate the management of deleted text begin all warehouse operators and telegraph companies deleted text end
3.23 new text begin entities within its jurisdiction new text end , the manner in which their businesses are conducted and the
3.24adequacies of the services which they are affording to the public, and make all appropriate
3.25orders relating to the continuation, termination, or modification of all services and facilities
3.26 deleted text begin with a view to properly promoting deleted text end new text begin necessary to ensure new text end the security and convenience of the
3.27public;
3.28(2) review and ascertain the reasonableness of tariffs of rates, fares, and charges, or any
3.29part or classification thereof, and prescribe the form and manner of filing, posting, and
3.30publication thereof;
3.31(3) prescribe uniform systems of keeping and rendering accounts and the time within
3.32which such systems shall be adopted;
4.1(4) order the issuance of franchises, permits or certificates of deleted text begin convenience and necessity deleted text end
4.2 new text begin need new text end .
4.3Sec. 9. Minnesota Statutes 2024, section 216B.027, subdivision 7, is amended to read:
4.4Subd. 7. Optional referendum. No cooperative shall be bound by the provisions of this
4.5section unless adoption has been approved at referendum using the petition and election
4.6procedures in section 216B.026. deleted text begin Within 60 days of May 19, 1983, the board of directors of deleted text end
4.7 deleted text begin each cooperative electric association shall notify the stockholders of the provisions of this deleted text end
4.8 deleted text begin section and shall explain the process for ratification by petition and election as provided in deleted text end
4.9 deleted text begin this subdivision. deleted text end
4.10Sec. 10. Minnesota Statutes 2024, section 216B.06, is amended to read:
4.11216B.06 RECEIVING DIFFERENT COMPENSATION.
4.12No public utility shall directly or indirectly, by any device whatsoever, or in any manner,
4.13charge, demand, collect, or receive from any person a greater or less compensation for any
4.14service rendered or to be rendered by the utility than that prescribed in the schedules of
4.15rates of the public utility applicable thereto when filed in the manner provided in Laws
4.161974, chapter 429, nor shall any person knowingly receive or accept any service from a
4.17public utility for a compensation greater or less than that prescribed in the schedules deleted text begin , provided deleted text end
4.18 deleted text begin that all rates being charged and collected by a public utility upon January 1, 1975, may be deleted text end
4.19 deleted text begin continued until schedules are filed deleted text end .
4.20Sec. 11. Minnesota Statutes 2024, section 216B.098, subdivision 2, is amended to read:
4.21Subd. 2. Budget billing plans. A utility shall offer a customer a budget billing plan for
4.22payment of charges for service, including adequate notice to customers prior to changing
4.23budget payment amounts. Municipal utilities having 3,000 or fewer customers are exempt
4.24from this requirement. deleted text begin Municipal utilities having more than 3,000 customers shall implement deleted text end
4.25 deleted text begin this requirement before July 1, 2003. deleted text end
4.26Sec. 12. Minnesota Statutes 2024, section 216B.16, subdivision 19, is amended to read:
4.27Subd. 19. Multiyear rate plan. (a) A public utility may propose, and the commission
4.28may approve, approve as modified, or reject, a multiyear rate plan as provided in this
4.29subdivision. The term "multiyear rate plan" refers to a plan establishing the rates the utility
4.30may charge for each year of the specified period of years, which cannot exceed five years,
4.31to be covered by the plan. A utility proposing a multiyear rate plan shall provide a general
5.1description of the utility's major planned investments over the plan period. The commission
5.2may also require the utility to provide a set of reasonable performance measures and
5.3incentives that are quantifiable, verifiable, and consistent with state energy policies. The
5.4commission may allow the utility to adjust recovery of its cost of capital or other costs in
5.5a reasonable manner within the plan period. The utility may propose:
5.6(1) recovery of the utility's forecasted rate base, based on a formula, a budget forecast,
5.7or a fixed escalation rate, individually or in combination. The forecasted rate base must
5.8include the utility's planned capital investments and investment-related costs, including
5.9income tax impacts, depreciation, and property taxes, as well as forecasted capacity-related
5.10costs from purchased power agreements that are not recovered through subdivision 7;
5.11(2) recovery of operations and maintenance expenses, based on an electricity-related
5.12price index or other formula;
5.13(3) tariffs that expand the products and services available to customers, including, but
5.14not limited to, an affordability rate for low-income residential customers; and
5.15(4) adjustments to the rates approved under the multiyear plan for rate changes that the
5.16commission determines to be just and reasonable, including, but not limited to, changes in
5.17the utility's cost of operating its nuclear facilities, or other significant investments not
5.18addressed in the plan.
5.19(b) A utility that has filed a petition with the commission to approve a multiyear rate
5.20plan may request to be allowed to implement interim rates for the first and second years of
5.21the multiyear plan. If the commission approves the request, interim rates shall be implemented
5.22in the same manner as allowed under subdivision 3.
5.23(c) The commission may approve a multiyear rate plan only if it finds that the plan
5.24establishes just and reasonable rates for the utility, applying the factors described in
5.25subdivision 6. Consistent with subdivision 4, the burden of proof to demonstrate that the
5.26multiyear rate plan is just and reasonable is on the public utility proposing the plan.
5.27(d) Rates charged under the multiyear rate plan must be based only upon the utility's
5.28reasonable and prudent costs of service over the term of the plan, as determined by the
5.29commission, provided that the costs are not being recovered elsewhere in rates. Rate
5.30adjustments authorized under subdivisions 6b and 7 may continue outside of a plan authorized
5.31under this subdivision.
5.32(e) The commission may, by order, establish terms, conditions, and procedures for a
5.33multiyear rate plan necessary to implement this section and ensure that rates remain just
6.1and reasonable during the course of the plan, including terms and procedures for rate
6.2adjustment. At any time prior to conclusion of a multiyear rate plan, the commission, upon
6.3its own motion or upon petition of any party, has the discretion to examine the reasonableness
6.4of the utility's rates under the plan, and adjust rates as necessary.
6.5(f) In reviewing a multiyear rate plan proposed in a general rate case under this section,
6.6the commission may extend the time requirements for issuance of a final determination
6.7prescribed in this section by an additional 90 days beyond its existing authority under
6.8subdivision 2, paragraph (f).
6.9 deleted text begin (g) A utility may not file a multiyear rate plan that would establish rates under the terms deleted text end
6.10 deleted text begin of the plan until after May 31, 2012. deleted text end
6.11 deleted text begin (h) deleted text end new text begin (g) new text end The commission may initiate a proceeding to determine a set of performance
6.12measures that can be used to assess a utility operating under a multiyear rate plan.
6.13Sec. 13. Minnesota Statutes 2024, section 216B.1611, subdivision 3a, is amended to read:
6.14Subd. 3a. Project information. (a) deleted text begin Beginning July 1, 2014, deleted text end Each electric utility shall
6.15request an applicant for interconnection of distributed renewable energy generation to
6.16provide the following information, in a format prescribed by the commissioner:
6.17(1) the nameplate capacity of the facility in the application;
6.18(2) the preincentive installed cost and cost components of the generation system at the
6.19facility;
6.20(3) the energy source of the facility; and
6.21(4) the zip code in which the facility is to be located.
6.22(b) The commissioner shall develop or identify a system to collect and process the
6.23information under this subdivision for each utility, and make non-project-specific data
6.24available to the public on a periodic basis as determined by the commissioner, and in a
6.25format determined by the commissioner. The commissioner may solicit proposals from
6.26outside parties to develop the system. The commissioner may only collect data authorized
6.27in paragraph (a), and may not require submission of any additional data that could be used
6.28to personally identify any individual applicant or utility customer.
6.29(c) Electric utilities collecting and transferring data under this subdivision are not
6.30responsible for the accuracy, completeness, or quality of the information under this
6.31subdivision.
7.1(d) Except as provided in paragraph (b), any information provided by an applicant to
7.2the commissioner under this subdivision is nonpublic data as defined in section 13.02,
7.3subdivision 9.
7.4Sec. 14. Minnesota Statutes 2024, section 216B.2412, is amended by adding a subdivision
7.5to read:
7.6 new text begin Subd. 4. Decoupling plans. A public utility may file a decoupling plan. The commission new text end
7.7 new text begin may approve, deny, or modify the decoupling plan consistent with the public interest. new text end
7.8Sec. 15. Minnesota Statutes 2024, section 216B.2422, subdivision 3, is amended to read:
7.9Subd. 3. Environmental costs. (a) The commission shall, to the extent practicable,
7.10quantify and establish a range of environmental costs associated with each method of
7.11electricity generation. A utility shall use the values established by the commission in
7.12conjunction with other external factors, including socioeconomic costs, when evaluating
7.13and selecting resource options in all proceedings before the commission, including resource
7.14plan and certificate of need proceedings.
7.15(b) The commission shall provisionally adopt and apply the draft cost of greenhouse gas
7.16emissions valuations presented in the United States Environmental Protection Agency's
7.17EPA External Review Draft of Report on the Social Cost of Greenhouse Gases: Estimates
7.18Incorporating Recent Scientific Advances, released in September 2022, including the time
7.19horizon, global estimates of damages, and the full range of discount rates from 2.5 to 1.5
7.20percent, with two percent as the central estimate. The commission shall adopt the estimates
7.21contained in the final version of the external review draft report when it becomes available.
7.22(c) If, at any time, the estimates adopted by the commission under paragraph (a) are
7.23exceeded by estimates released by the federal Interagency Working Group on the Social
7.24Cost of Greenhouse Gases or its successors, the commission shall adopt the working group
7.25estimates.
7.26 deleted text begin (d) The commission shall establish interim environmental cost values associated with deleted text end
7.27 deleted text begin each method of electricity generation by March 1, 1994. These values expire on the date deleted text end
7.28 deleted text begin the commission establishes environmental cost values under paragraph (a). deleted text end
7.29Sec. 16. Minnesota Statutes 2024, section 216B.27, subdivision 1, is amended to read:
7.30Subdivision 1. Applying for rehearing new text begin or reconsideration new text end . Within 20 days after the
7.31service by the commission of any decision constituting an order or determination, any party
7.32to the proceeding and any other person, aggrieved by the decision and directly affected
8.1thereby, may apply to the commission for a rehearing new text begin or reconsideration new text end in respect to any
8.2matters determined in the decision. The commission may grant and hold a rehearing new text begin or new text end
8.3 new text begin reconsideration new text end on the matters, or upon any of them as it may specify in the order granting
8.4the rehearing new text begin or reconsideration new text end , if in its judgment sufficient reason therefor exists.
8.5Sec. 17. Minnesota Statutes 2024, section 216B.27, subdivision 2, is amended to read:
8.6Subd. 2. Contents of application; condition precedent for review. The application
8.7for a rehearing new text begin or reconsideration new text end shall set forth specifically the grounds on which the
8.8applicant contends the decision is unlawful or unreasonable. No cause of action arising out
8.9of any decision constituting an order or determination of the commission or any proceeding
8.10for the judicial review thereof shall accrue in any court to any person or corporation unless
8.11the plaintiff or petitioner in the action or proceeding within 20 days after the service of the
8.12decision, shall have made application to the commission for a rehearing new text begin or reconsideration new text end
8.13in the proceeding in which the decision was made. No person or corporation shall in any
8.14court urge or rely on any ground not so set forth in the application for rehearing new text begin or new text end
8.15 new text begin reconsideration new text end .
8.16Sec. 18. Minnesota Statutes 2024, section 216B.27, subdivision 3, is amended to read:
8.17Subd. 3. Rules; procedural requirements; commission's authority. Applications for
8.18rehearing new text begin or reconsideration new text end shall be governed by general rules which the commission may
8.19establish. In case a rehearing new text begin or reconsideration new text end is granted the proceedings shall conform
8.20as nearly as may be to the proceedings in an original hearing, except as the commission
8.21may otherwise direct. If in the commission's judgment, after the rehearing new text begin or reconsideration new text end ,
8.22it shall appear that the original decision, order, or determination is in any respect unlawful
8.23or unreasonable, the commission may reverse, change, modify, or suspend the original
8.24action accordingly. Any decision, order, or determination made after the rehearing new text begin or new text end
8.25 new text begin reconsideration new text end reversing, changing, modifying, or suspending the original determination
8.26shall have the same force and effect as an original decision, order, or determination. Only
8.27one rehearing new text begin or reconsideration new text end shall be granted by the commission; but this shall not be
8.28construed to prevent any party from filing a new application or complaint. No order of the
8.29commission shall become effective while an application for a rehearing new text begin or reconsideration, new text end
8.30or a rehearing new text begin or reconsideration proceeding, new text end is pending and until ten days after the
8.31application for a rehearing new text begin or reconsideration new text end is either denied, expressly or by implication,
8.32or the commission has announced its final determination on rehearing new text begin or reconsideration new text end .
9.1Sec. 19. Minnesota Statutes 2024, section 216B.27, subdivision 4, is amended to read:
9.2Subd. 4. Deadline to grant application. Any application for a rehearing new text begin or new text end
9.3 new text begin reconsideration new text end not granted within 60 days from the date of filing thereof, shall be deemed
9.4denied.
9.5Sec. 20. Minnesota Statutes 2024, section 216B.27, subdivision 5, is amended to read:
9.6Subd. 5. Effect of decision on application. It is hereby declared that the legislative
9.7powers of the state, insofar as they are involved in the issuance of orders and decisions by
9.8the commission, have not been completely exercised until the commission has acted upon
9.9an application for rehearing new text begin or reconsideration new text end , as provided for by this section and by the
9.10rules of the commission, or until the application for rehearing new text begin or reconsideration new text end has been
9.11denied by implication, as above provided for.
9.12Sec. 21. Minnesota Statutes 2024, section 216B.43, is amended to read:
9.13216B.43 HEARING ON COMPLAINT.
9.14Upon the filing of an application under section 216B.42 or upon complaint by an affected
9.15utility that the provisions of sections 216B.39 to 216B.42 have been violated, the commission
9.16shall hold a hearing, upon notice, within deleted text begin 30 deleted text end new text begin 60 new text end days after the filing of the complaint, and
9.17shall render its decision within 30 days after the hearing.
9.18Sec. 22. Minnesota Statutes 2024, section 216B.62, subdivision 3a, is amended to read:
9.19Subd. 3a. Supplemental staffing assessment. In addition to other assessments in
9.20subdivision 3, the commission may assess up to $800,000 per year for supplemental staffing
9.21to implement requirements of this chapter. The amount in this subdivision shall be assessed
9.22to the several public utilities in proportion to their respective gross operating revenues from
9.23retail sales of gas or electric service within the state during the last calendar year and shall
9.24be deposited into an account in the special revenue fund new text begin and appropriated to the commission new text end .
9.25An assessment made under this subdivision is not subject to the cap on assessments provided
9.26in subdivision 3 or any other law.
9.27Sec. 23. new text begin REPEALER. new text end
9.28 new text begin Minnesota Statutes 2024, sections 216B.1681; 216B.1695; and 216B.2412, subdivision new text end
9.29 new text begin 3, are repealed. new text end APPENDIX Repealed Minnesota Statutes: 26-07709 216B.1681 CURTAILMENT PAYMENTS. The commission shall conduct a study of curtailment payments for wind energy projects to assess whether utilities are unduly discriminating among project ownership structures in regard to the contractual availability of curtailment payments. The commission shall submit the study to the chairs and ranking minority members of the senate and house of representatives committees with primary jurisdiction over energy policy by January 15, 2008. 216B.1695 ENVIRONMENTAL PROJECTS; ADVANCE DETERMINATION OF PRUDENCE. Subdivision 1. Qualifying project. A public utility may petition the commission for an advance determination of prudence for a project undertaken to comply with federal or state air quality standards of states in which the utility's electric generation facilities are located, if the project has an expected jurisdictional cost to Minnesota ratepayers of at least $10,000,000. A project is undertaken to comply with federal or state air quality standards if it is required: (1) by the state in which the generation facility is located in a state implementation plan, permit, or order; or (2) to comply with section 111 or 112 of the federal Clean Air Act, United States Code, title 42, section 7411 or 7412. Subd. 2. Regulatory cost assessments and reports. (a) A utility requesting an advance determination under subdivision 1 must, as part of the evidence required when filing a petition under subdivision 3, provide to the Public Utilities Commission and the Pollution Control Agency an assessment of all anticipated state and federal environmental regulations related to the production of electricity from the utility's facility subject to the filing, including regulations relating to: (1) air pollution by nitrogen oxide and sulphur dioxide, including an assumption that Minnesota will be included in the federal Clean Air Interstate Rule region, hazardous air pollutants, carbon dioxide, particulates, and ozone; (2) coal waste; and (3) water consumption and water pollution. (b) In addition, the utility shall provide an assessment of the financial and operational impacts of these pending regulations applicable to the generating facility that is the subject of the filing and provide a range of regulatory response scenarios that include, but are not limited to: (1) the installation of pollution control equipment; (2) the benefits of the retirement or repowering of the plant that is the subject of the filing with cleaner fuels considering the costs of complying with state and federal environmental regulations; and (3) the use of pollution allowances to achieve compliance. (c) The utility shall consult with interested stakeholders in establishing the scope of the regulatory, financial, and operational assessments prior to or during the 60-day period of the notice under subdivision 4. Subd. 3. Petition. A petition filed under this section must include a description of the project, evidence supporting the project's reasonableness, a discussion of project alternatives, a project implementation schedule, a cost estimate and support for the reasonableness of the estimated cost, and a description of the public utility's efforts to ensure the lowest reasonable costs. Following receipt of the Pollution Control Agency's verification under subdivision 4, the commission shall allow opportunity for oral and written comment on the petition. The commission shall make a final determination on the petition within ten months of its filing date. The commission must make findings in support of its determination. Subd. 4. Verification. At least 60 days prior to filing a petition to the commission under subdivision 3, the utility shall file notice with the Pollution Control Agency that describes the project and how it qualifies under subdivision 1. The Pollution Control Agency shall, within 60 days of receipt of the notice, verify that the project qualifies under subdivision 1, and shall forward written verification to the commission. Subd. 5. Cost recovery. The utility may begin recovery of costs that have been incurred by the utility in connection with implementation of the project in the next rate case following an advance determination of prudence or in a rider approved under section 216B.1692. The commission shall review the costs incurred by the utility for the project. The utility must show that the project costs are reasonable and necessary, and demonstrate its efforts to ensure the lowest reasonable project costs. Notwithstanding the commission's prior determination of prudence, it may accept, modify, or reject any of the project costs. The commission may determine whether to require an allowance for funds used during construction offset. Subd. 5a. Rate of return. The return on investment in the rider shall be at the level approved by the commission in the public utility's last general rate case, unless the commission determines that a different rate of return is in the public interest. Subd. 6. Expiration. A petition for an advance determination of prudence may not be filed after December 31, 2015. 216B.2412 DECOUPLING OF ENERGY SALES FROM REVENUES. Subd. 3. Pilot programs. The commission shall allow one or more rate-regulated utilities to participate in a pilot program to assess the merits of a rate-decoupling strategy to promote energy efficiency and conservation. Each pilot program must utilize the criteria and standards established in subdivision 2 and be designed to determine whether a rate-decoupling strategy achieves energy savings. On or before a date established by the commission, the commission shall require electric and gas utilities that intend to implement a decoupling program to file a decoupling pilot plan, which shall be approved or approved as modified by the commission. A pilot program may not exceed three years in length. Any extension beyond three years can only be approved in a general rate case, unless that decoupling program was previously approved as part of a general rate case.
Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.
Progress through the legislative process
In Committee