HF4933
Light rail transit project notice required.
Legislative Session 94 (2025-2026)
Related bill: SF5112
AI Generated Summary
Purpose
This bill would require certain light rail transit projects to notify the Minnesota Legislature if key cost or schedule details change. The goal is to improve transparency and keep lawmakers informed about significant project changes as they occur.
Main Provisions
- Adds a new requirement (Subdivision 5) to Minnesota law to mandate notice to the legislature about major changes to a light rail transit project.
- Defines a “reference date” as the earliest date when a project has:
- a total project cost estimate,
- a schedule including an estimated date for substantial completion of construction, and
- federal approval to enter the engineering phase (or starts similar final design activities).
- Requires a responsible authority to notify the chairs and ranking minority members of the legislative committees with jurisdiction over transportation policy and finance within seven calendar days of a change meeting any of these conditions:
- the total project cost estimate increases by five percent or more above the most recently specified estimate or the estimate as of the reference date, or
- the anticipated substantial completion date is delayed by six months or more beyond the most recently specified completion date or the date as of the reference date.
- The notification must at a minimum include:
- an overview of the project cost estimate and the schedule, and
- an explanation of the reasons for the cost increase, delay, or both.
- Applies specifically to light rail transit projects for which a reference date is applicable.
Key Definitions and Terms (as used in the bill)
- Light rail transit project
- Total project cost estimate
- Schedule with an estimated date for substantial completion of construction
- Federal approval to enter the engineering phase (or equivalent final design activity)
- Reference date
- Responsible authority
- Chairs and ranking minority members of the legislative committees with jurisdiction over transportation policy and finance
- Seven calendar days (notification deadline)
- Five percent (cost increase threshold)
- Six months (delay threshold)
Significance and Changes to Law
- Creates a formal, legislator-facing notification requirement for notable cost increases or schedule delays in light rail projects.
- Establishes a defined reference date to determine when changes trigger the notification obligation.
- Improves accountability by ensuring lawmakers receive timely information about project changes and the reasons behind them.
Scope and Applicability
- The notification requirement applies to light rail transit projects where a reference date is applicable, and only triggers when specified cost or schedule changes occur.
Relevant Terms light rail transit project; total project cost estimate; schedule; substantial completion of construction; federal approval to enter the engineering phase; reference date; responsible authority; chairs; ranking minority members; transportation policy and finance; seven calendar days; five percent; six months; notification; overview of cost estimate; explanation of the reasons for change.
Actions
| Date | Chamber | Where | Type | Name | Committee Name |
|---|---|---|---|---|---|
| April 09, 2026 | House | Action | Introduction and first reading, referred to | Transportation Finance and Policy | |
| Showing the 5 most recent stages. This bill has 1 stages in total. Log in to view all stages | |||||
Citations
You must be logged in to view citations.
Progress through the legislative process
In Committee
Sponsors
You must be logged in to view sponsors.