SF5112

Notice requirement to the legislature regarding certain light rail transit project changes
Legislative Session 94 (2025-2026)

Related bill: HF4933

AI Generated Summary

Purpose

This bill adds a new rule that requires certain light rail projects to notify Minnesota’s lawmakers when big changes happen to their cost or schedule. The goal is to improve transparency and oversight of major transit projects.

Key terms and definitions

  • reference date: the earliest date a light rail project has (a) a total project cost estimate, (b) a schedule with an estimated date for substantial completion, and (c) federal approval to enter the engineering phase or to begin final design activities.
  • total project cost estimate: the overall budget projection for the light rail project.
  • substantial completion: the point when the project is nearly finished and ready for final steps.
  • engineering phase / final design activities: stages where detailed plans and designs are prepared.
  • responsible authority: the group responsible for managing the light rail project.
  • chairs and ranking minority members: the top leaders from the legislative transportation policy and finance committees who receive the notice.

Main provisions

  • The bill adds a new subdivision (Subd. 5) to the current law (section 473.3999) to establish the notice requirement.
  • For a light rail transit project, once a responsible authority determines that:
    • the total project cost estimate is increased by 5% or more (compared to the most recently specified estimate or the estimate as of the reference date), or
    • the anticipated substantial completion date is delayed by six months or more beyond the date most recently specified or as of the reference date, the authority must notify the chairs and ranking minority members of the relevant legislative transportation committees within seven calendar days.
  • The notification must include:
    • an overview of the project cost estimate and the schedule, and
    • an explanation of the reasons for changes in cost or delays (or both).

Scope and applicability

  • The notice requirement applies to light rail transit projects that have a defined reference date (as described above).
  • The rule is triggered by changes to cost or schedule, and the notification is sent to the specified legislative leaders within seven days of the change.

Significance and potential impact

  • Creates a formal, timely channel for lawmakers to be informed about major cost increases or schedule delays in light rail projects.
  • Encourages transparency in project planning and budgeting.
  • Aligns project management with legislative oversight requirements.

Changes to current law

  • Adds a new subdivision (Subd. 5) to Minnesota Statutes 2024 section 473.3999, establishing the notification requirement.
  • Clarifies how the reference date is used to determine trigger events for the notice.
  • Integrates with existing definitions and sections related to light rail projects.

Relevant Terms reference date light rail transit project cost estimate total project cost estimate substantial completion engineering phase final design activities notice to legislature chairs ranking minority members legislative committees transportation policy and finance responsible authority cost increase schedule delay six months five percent notification requirements

Bill text versions

Showing the most recent version. There are  1  total versions. You must be logged in  to view additional bill text versions.

Actions

DateChamberWhereTypeNameCommittee Name
April 13, 2026SenateActionIntroduction and first reading
April 13, 2026SenateActionReferred toTransportation
Showing the 5  most recent stages. This bill has 2  stages in total. Log in to view all stages

Citations

You must be logged in  to view citations.

Progress through the legislative process

17%
In Committee

Sponsors

You must be logged in  to view sponsors.

Loading…