HF5036
Duluth International Airport improvements funding provided, and money appropriated.
Legislative Session 94 (2025-2026)
Related bill: SF5222
AI Generated Summary
Purpose
- Provide a one-time financial appropriation to support improvements at Duluth International Airport.
- Specifically, to fund a project for a new air traffic control tower and related facilities.
Main Provisions
- Funds and timing: $4,000,000 in fiscal year 2027 from the state airports fund.
- Recipient and process: A grant from the Commissioner of Transportation to the Duluth Airport Authority to manage the project.
- Project scope: Design, construct, furnish, and equip a new air traffic control tower and a base building, including associated offices, workspaces, equipment rooms, and logistic support spaces.
- Site and support work: Site preparation including demolition of obsolete buildings, construction and installation of utilities, a stormwater retention system, and replacement of an existing fuel tank.
- Federal funding match: A portion of the appropriation must be used as a match to federal funding for the project.
- Restrictions on uses of the funds: The commissioner must not use any amount of this appropriation for administrative costs, despite other rules about administrative spending.
- Relationship to prior funding: This is in addition to a separate appropriation from Laws 2025 First Special Session (chapter 8, article 1, section 2, subdivision 2, paragraph a, clause 1).
- Status and duration: This is a one-time appropriation and remains available through June 30, 2028.
Significance / What this means
- Improves airport capacity and safety by adding a new air traffic control tower and related facilities.
- Encourages leveraging federal funds through a required match.
- Keeps the funds dedicated to the project itself (no administrative costs) and provides a clear deadline for use.
Changes to Existing Law (notable legal effect)
- Introduces a specific prohibition on using this appropriation for administrative costs, via a not-withstanding clause, indicating funds must go toward the project itself rather than admin expenses.
- Adds an additional, separate funding allocation for Duluth International Airport beyond previously approved appropriations.
Relevant terms - appropriation - state airports fund - Duluth International Airport - Duluth Airport Authority - air traffic control tower - base building - grant - design - construction - furnish - equip - offices - utilities - stormwater retention system - fuel tank replacement - site preparation - demolition - federal funding match - administrative costs - Minnesota Statutes 16B.98 subdivision 14 - one-time appropriation - fiscal year 2027 - June 30, 2028 - commissioner of transportation - Laws 2025 First Special Session chapter 8 article 1 section 2 subdivision 2 paragraph a clause 1 - Transportation Finance and Policy (committee)
Actions
| Date | Chamber | Where | Type | Name | Committee Name |
|---|---|---|---|---|---|
| April 20, 2026 | House | Action | Introduction and first reading, referred to | Transportation Finance and Policy | |
| May 07, 2026 | House | Action | Author added |
Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.