HF185
Resilient pavement program established for certain trunk highway project modifications to pavement design, and money appropriated.
Legislative Session 94 (2025-2026)
Related bill: SF1487
Bill text
(underlined = new law, struck through = current law the bill removes)
1.1A bill for an act
1.2relating to transportation; establishing a resilient pavement program for certain
1.3trunk highway project modifications to pavement design life; appropriating money;
1.4proposing coding for new law in Minnesota Statutes, chapter 174.
1.5BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.6Section 1. new text begin [174.205] RESILIENT PAVEMENT PROGRAM. new text end
1.7 new text begin Subdivision 1. Definitions. (a) For purposes of this section, the following terms have new text end
1.8 new text begin the meanings given. new text end
1.9 new text begin (b) "Baseline project" means a trunk highway project without revision to pavement new text end
1.10 new text begin design life. new text end
1.11 new text begin (c) "Commissioner" means the commissioner of transportation. new text end
1.12 new text begin (d) "Modified project" means a project that is revised or under a revision analysis to new text end
1.13 new text begin contain a modified pavement design life using funds provided under the program. new text end
1.14 new text begin (e) "Pavement cost" means the estimated total cost of pavement items for the project, new text end
1.15 new text begin in conformance with standard specifications for construction established by the commissioner. new text end
1.16 new text begin (f) "Program" means the resilient pavement program under this section. new text end
1.17 new text begin Subd. 2. Program established. Subject to available funds, the commissioner must new text end
1.18 new text begin establish a resilient pavement program to provide supplemental funding for revisions to new text end
1.19 new text begin pavement design of trunk highway projects on the basis of long-term cost effectiveness. new text end
1.20 new text begin Subd. 3. Administration. (a) In implementing the program, the commissioner must: (1) new text end
1.21 new text begin establish procedures for identification, analysis, and selection of projects that receive funding new text end
2.1 new text begin and are accordingly revised in the pavement design; and (2) specify a modified pavement new text end
2.2 new text begin design life of at least 50 years for modified projects. new text end
2.3 new text begin (b) The commissioner must determine pavement design life using the current standard new text end
2.4 new text begin models used by the department for pavement design. new text end
2.5 new text begin Subd. 4. Project eligibility; cost effectiveness. (a) To be eligible for funds under the new text end
2.6 new text begin program, a project must: new text end
2.7 new text begin (1) be for trunk highway construction, reconstruction, maintenance, or improvement; new text end
2.8 new text begin (2) be included in a prior or the current state transportation improvement program or new text end
2.9 new text begin capital highway investment plan with a proposed design life of less than or equal to 20 new text end
2.10 new text begin years; new text end
2.11 new text begin (3) be a modified project with a pavement design life as specified under subdivision 3, new text end
2.12 new text begin paragraph (a), clause (2); and new text end
2.13 new text begin (4) have a cost effectiveness ratio, as calculated under paragraph (b), that equals or is new text end
2.14 new text begin greater than two. new text end
2.15 new text begin (b) The cost effectiveness ratio is calculated as: new text end
2.16 new text begin (1) the pavement cost of the baseline project, divided by the pavement design life of the new text end
2.17 new text begin baseline project; divided by new text end
2.18 new text begin (2) the pavement cost of the modified project, divided by the modified pavement design new text end
2.19 new text begin life. new text end
2.20 new text begin Subd. 5. Use of funds. (a) For a project selected under the program, the commissioner new text end
2.21 new text begin may expend program funds for up to 110 percent of the difference in anticipated pavement new text end
2.22 new text begin costs between the modified project and the baseline project. new text end
2.23 new text begin (b) The commissioner may expend up to one-third of the funds on projects located wholly new text end
2.24 new text begin or substantially inside the Department of Transportation metropolitan district, as calculated new text end
2.25 new text begin using total funds under the program over (1) the current fiscal year, and (2) the latest prior new text end
2.26 new text begin two years in which funds are allocated. new text end
2.27 new text begin (c) The commissioner must not expend funds under the program for program delivery. new text end
2.28 new text begin Subd. 6. Public information. The commissioner must publish information regarding new text end
2.29 new text begin the program on the department's website. The information must include: new text end
2.30 new text begin (1) a description of program implementation; new text end
2.31 new text begin (2) identification of projects analyzed and selected under the program; and new text end
3.1 new text begin (3) for each project selected, an overview that includes a brief project description, the new text end
3.2 new text begin pavement design changes, and information on expenditures from program funds. new text end
3.3Sec. 2. new text begin APPROPRIATION; RESILIENT PAVEMENT PROGRAM. new text end
3.4 new text begin $150,000,000 in fiscal year 2027 is appropriated from the general fund to the new text end
3.5 new text begin commissioner of transportation for the resilient pavement program under Minnesota Statutes, new text end
3.6 new text begin section 174.205. This is a onetime appropriation and is available until June 30, 2035. Any new text end
3.7 new text begin excess amount cancels to the general fund. new text end
Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.
Progress through the legislative process
In Committee